Formwork Shoring (Steel Tube Posts) Check

Three temporary works checks selected by type: steel tube formwork shoring posts (slenderness and axial capacity), braced excavation struts and walers under apparent earth pressure, and scaffold post buckling with wall tie force under wind and wall tie spacing limits.

Design basis for this page ▾
MOTC (Taiwan) Highway Construction Specifications (2013-01) Sec. 01525, 2.3; post allowable axial force per MOTC (Taiwan) Highway Bridge Design Code (2009 provisions) Ch. 9 allowable stress design scaled to a safety factor of 2.5; Taiwan Standards for Construction Safety and Health Facilities Art. 131

Design basis as reported by the calculation core: MOTC (Taiwan) Highway Construction Specifications (2013-01) Sec. 01525, 2.3; post allowable axial force per MOTC (Taiwan) Highway Bridge Design Code (2009 provisions) Ch. 9 allowable stress design scaled to a safety factor of 2.5; Taiwan Standards for Construction Safety and Health Facilities Art. 131
Loads, allowable stresses and thresholds follow the Taiwan specifications named in the basis line; they are not BS 5975, OSHA or other national rules. Use the result as a reference calculation.

Recalculates in your browser as you edit inputs; Free sample Word report and DXF for this calculator; With a license: formal Word and DXF export, plus online project reports from the Project List.

Interactive Engineering Workstation (SI Units, Reference Calculation)
SI units (reference calculation)
Free Samples and Pricing
A public sample produced by the production service from this page's standard example and sealed with a verification code: open it in Word or AutoCAD and check it on the Verify page. Not for PE sealing or submittal.
Single-export pass: US$19 for one calculator, 3 formal exports in total within 24 hours of the first; full credit toward an upgrade within 30 days, full refund before the first export
Single-export passes (one calculator, 3 exports within 24 hours), 30-day passes, annual plans and perpetual licenses; printable quotes for purchase orders.
Formal export and the Project List are on the workbench toolbar above:
Licensed users can formally export this calculator's Word report (with a verification code and server time witness) and AutoCAD DXF drawing, or add several calculators to the free Project List and export a multi-chapter project report online, with nothing to install on a Mac. Projects with DEM terrain or GIS files can run in the heavy cloud computation or in the HydroStudio desktop edition.
The summary lists the basis, key results and check verdicts; its first line marks it as an online preview, not for PE sealing or submittal.
Download the Offline Workbench (Single HTML File, 39 Tools)
No install and no email required. It contains the same calculation core as this site; results are also a preview, not for sealed submittals.

Check Summary Preview (Software Format; Auto-Populated)

Formwork Shoring (Steel Tube Posts) Check: check summary (software format)
Calculation basis: MOTC (Taiwan) Highway Construction Specifications (2013-01) Sec. 01525, 2.3; post allowable axial force per MOTC (Taiwan) Highway Bridge Design Code (2009 provisions) Ch. 9 allowable stress design scaled to a safety factor of 2.5; Taiwan Standards for Construction Safety and Health Facilities Art. 131
Check item Trial value Status
Dead load + construction live load1306.50 kgf/m² ≥ 490.00 kgf/m²OK
Construction live load100.00 kgf/m² ≥ 100.00 kgf/m²OK
Concrete unit weight2570.00 kgf/m³ ≥ 2570.00 kgf/m³OK
Post slenderness KL/r88.13 ≤ 180.00OK
Post axial force ≤ allowable axial force16.21 kN ≤ 36.63 kNOK
Vertical spacing of horizontal ties1.80 m ≤ 2.00 mOK

Summary of the online calculation (software format) for checking by the designer and an independent checker. Final submittals require review and seal by the licensed Professional Engineer in responsible charge.

Desktop edition: calculation reports and cross-module quantity reconciliation

1. Calculation reports: with a license, the desktop edition writes Word (.docx) and Excel (.xlsx) calculation reports and DXF drawings without the trial watermark, listing the inputs, the equations used and the results; in trial mode the step-by-step detail is hidden. For this calculator alone, licensed users can also sign in on the calculator above and formally export a single-tool Word report (with a verification code) and DXF drawing. The Pro plan (all modules) is US$990 per year; see Pricing for monthly, perpetual and team plans.
2. Cross-module reconciliation: desktop project runs carry the design peak flow into downstream channel, culvert and bridge hydraulics; terrain cut/fill into the earthwork balance, cost and carbon tables; structural concrete, formwork and rebar take-off into the cost and carbon tables; slope and excavation safety-factor thresholds into construction monitoring trigger levels.
3. Agency plan reviewers and university faculty can request a complimentary review or teaching license (link below).

Desktop pricing (Pro US$990/yr) Download the desktop trial Complimentary license for agency reviewers and faculty
Scope and responsibility: This page is a single-calculator trial run; cross-module quantity reconciliation is done in desktop project runs. Problems outside this calculator's scope (see the FAQ) need an appropriate analysis method. Final submittals require review and seal by a licensed Professional Engineer. Where the inputs reach them, the page flags OSHA thresholds: excavations deeper than 20 ft (Subpart P, Appendix B), tube and coupler or fabricated frame scaffolds over 125 ft (29 CFR 1926.452) and tiered single post shores (29 CFR 1926.703(b)(8)). The calculations themselves follow the Taiwan specifications named in the basis line.

Standard example (calculation core defaults)

The worked example below was computed by the calculation core when this page was built; entering the same inputs above reproduces it. Verification cases, tolerances and actual differences for the calculation core are listed on the Benchmarks page.

The standard example uses the default inputs of the calculation core. Every number below was produced by the core when this page was built; nothing on this page is computed by hand.

Every number in this example was produced by the calculation core (WebAssembly) when this page was built. This calculator computes to the documents named in its basis line and works in SI units; use the unit button in the calculator to view US customary equivalents. Basis reported by the core: MOTC (Taiwan) Highway Construction Specifications (2013-01) Sec. 01525, 2.3; post allowable axial force per MOTC (Taiwan) Highway Bridge Design Code (2009 provisions) Ch. 9 allowable stress design scaled to a safety factor of 2.5; Taiwan Standards for Construction Safety and Health Facilities Art. 131

1. Input Parameters

Design ParameterValueUnit
Temporary Works TypeFormwork shoring (steel tube posts)—
Thickness of Concrete Slab to be Placed0.45m
Self-Weight of Formwork and Shoring50kgf/m²
Post Spacing, Longitudinal1m
Post Spacing, Transverse1m
Steel Tube Post Outside Diameter60.5mm
Steel Tube Post Wall Thickness2.8mm
Total Shoring Post Height5.4m
Vertical Spacing of Horizontal Ties1.8m
Formwork Area per Pour350m²
Tiered Single Post ShoresNo—

2. Computed Results (calculation core output)

OutputResult
Post axial force16.21 kN
Post allowable axial force (safety factor 2.5)36.63 kN
Post slenderness KL/r88.1
Design vertical load1653 kgf/m²
Minimum design horizontal force per post0.24 kN

Verification Checks (calculation core output)

Verification ItemComputed ResultGoverning Limit / CriterionStatusBasis
Dead load + construction live load1306.50 kgf/m²≥ 490.00 kgf/m²PASSMOTC (Taiwan) Highway Construction Specifications (2013-01) Sec. 01525, 2.3 (2.3.3: at least 490 kgf/m²)
Construction live load100.00 kgf/m²≥ 100.00 kgf/m²PASSMOTC (Taiwan) Highway Construction Specifications (2013-01) Sec. 01525, 2.3 (2.3.3: uniform load not less than 100 kgf/m²)
Concrete unit weight2570.00 kgf/m³≥ 2570.00 kgf/m³PASSMOTC (Taiwan) Highway Construction Specifications (2013-01) Sec. 01525, 2.3 (2.3.3: not less than 2,570 kgf/m³)
Post slenderness KL/r88.13≤ 180.00PASSMOTC (Taiwan) Highway Construction Specifications (2013-01) Sec. 01525, 2.3 (Table 01525-6: main compression steel members ≤ 180)
Post axial force ≤ allowable axial force16.21 kN≤ 36.63 kNPASSMOTC (Taiwan) Highway Construction Specifications (2013-01) Sec. 01525, 2.3 (2.3.5: safety factor not less than 2.5); MOTC (Taiwan) Highway Bridge Design Code (2009 provisions) Ch. 9 allowable stress design Table 9.8
Vertical spacing of horizontal ties1.80 m≤ 2.00 mPASSMOTC (Taiwan) Highway Construction Specifications (2013-01) Sec. 01525, 2.3 (adjustable steel tube posts higher than 3.5 m need horizontal ties in both directions every 2 m)

3. Calculation Steps (calculation core output, SI units)

[HyGeoWorks online preview - not for PE sealing or submittal]
Vertical load: dead 1206 + construction live 100 + impact 347 = 1653 kgf/m²; tributary area 1.00 m² per post → post axial force 16.21 kN
Tube A = 5.08 cm², r = 2.04 cm, KL/r = 88.1 → allowable axial force 36.63 kN; minimum design horizontal force 0.24 kN per post

Assumptions and Limits Stated by the Calculation Core

Frequently Asked Questions

Common questions about this calculator and its basis are answered below. Final submittals require review and seal by a licensed Professional Engineer.

Which design basis does this calculator apply?

MOTC (Taiwan) Highway Construction Specifications (2013-01) Sec. 01525, 2.3; post allowable axial force per MOTC (Taiwan) Highway Bridge Design Code (2009 provisions) Ch. 9 allowable stress design scaled to a safety factor of 2.5; Taiwan Standards for Construction Safety and Health Facilities Art. 131. Loads, allowable stresses and thresholds follow the Taiwan specifications named in the basis line; they are not BS 5975, OSHA or other national rules. Use the result as a reference calculation.

What assumptions and limits does the calculation core state for this tool?

Loads per MOTC (Taiwan) Highway Construction Specifications (2013-01) Sec. 01525, 2.3: dead load (concrete 1156 kgf/m² + formwork 50 kgf/m²), construction live load 100 kgf/m², impact load (30% of the placed concrete weight) 347 kgf/m²; the minimum design horizontal force of each support member is 2% of the supported dead load (0.24 kN per post), which must be carried by braces or ties to a stable support. Not included: wind, earthquake, stream flow force, concentrated loads from construction equipment, overturning stability (safety factor 1.2), deflection (L/240), prefabricated shoring frames (per the manufacturer's test data; working load not more than 40% of the maximum tested load). Taiwan Standards for Construction Safety and Health Facilities Art. 131: formwork shoring with a height of 7 m or more and an area of 330 m² or more must be designed and signed off by a full-time engineer or a licensed professional engineer; this tool does not apply the Ministry of the Interior (Taiwan) Design Code for Scaffolds and Formwork Shoring; check it separately.

Where is the calculation performed, and can the result be sealed or submitted?

The calculation runs in your browser, in the same WebAssembly calculation core this page loads. The result is an online preview: its first line reads "[HyGeoWorks online preview - not for PE sealing or submittal]".

Can I recalculate without a network connection?

Yes. "Download the offline workbench" on this page saves one HTML file that contains the workbench and the same calculation core; opened from disk it recalculates without a network connection.

USD Pricing · Checkout by Stripe · Printable USD Quotation

From the Online Preview to the HydroStudio Desktop Edition: Reports Without the Trial Watermark

The free online preview is not for PE sealing or submittal and has no Word report, DXF drawing or verification code. Licensed users can sign in on the calculator and formally export a single-tool Word report (with a verification code) and DXF drawing. Several calculators can be combined in the Project List and exported online as a multi-chapter project report, and projects with terrain or GIS files can run in the heavy cloud computation. For interactive 2D models and large simulations, the HydroStudio desktop edition (Windows 10/11, 64-bit) opens the exported .toml project and, with a license, writes report.docx, a report.xlsx with live formulas and DXF drawings without the trial watermark. Sealing and submittal remain the responsibility of the licensed engineer.

Monthly
Pro monthly
$119 / month
One discipline: $69 / month. Renews monthly until canceled; cancel any time before the next renewal and keep using it to the end of the paid month.
Buy monthly ($119/mo)
30 days
30-day pass
$79 / 30 days, one discipline
All modules: $135. One payment; it does not renew. The pass fee can be credited once toward an annual or perpetual license of the same discipline or a higher plan bought within 30 days after the pass ends, with the same email and in the same currency.
Buy a 30-day pass (from $79)
Quotation
Printable USD quotation
For any plan, including Firm (from 3 seats) and Enterprise (from 10 seats), which are sold only to businesses and other organizations, not to individual buyers: print the quotation or save it as a PDF for your purchasing process.
Request a printable USD quotation

Compare all plans, including 90-day passes and perpetual licenses

Checkout is processed by Stripe; a tax ID can be entered at checkout, and for one-time payments Stripe issues an invoice showing the buyer's name and tax ID. Procurement follows your organization's own rules.

Explore All 31 Tools (20 US Customary + 11 Reference: Basis Stated on Each Page)

Need to edit terrain, 2D flood models and design alternatives interactively on your computer, or see 3D views drawn from your project data? Use the HydroStudio desktop edition:
Download the Desktop Trial
No credit card or phone number is needed to download. Without a license it runs as a trial: local calculation and 3D viewing work, exported reports and drawings carry a trial watermark (not for submittal), and some built-in data libraries are limited. Plans and prices are on the Pricing page.