Elasto-Plastic Diaphragm Wall Staged Excavation (Beam on Springs)
Staged excavation of a strutted diaphragm wall on elasto-plastic soil springs with preloaded struts: wall deflection, bending moment and shear envelopes, and the flexural and shear resistance of the wall reinforcement.
Design basis as reported by the calculation core: Taiwan Building Foundation Design Code (2023) commentary 8.7.3, Fig. C8.7-5 elasto-plastic subgrade reaction method; Taiwan Design Code for Concrete Structures (2023; ACI 318-19 framework) Chs. 21, 22
The analysis method and the reinforced concrete checks follow the Taiwan codes named in the basis line. Two soil layers, three excavation stages and two strut levels are modelled. The deflection control value (default 0.5% of the final excavation depth) and the flexural stiffness factor (default 0.70 Ec·Ig) are inputs, not statutory limits. Strengths are entered in kgf/cm².
Recalculates in your browser as you edit inputs; Free sample Word report and DXF for this calculator; With a license: formal Word and DXF export, plus online project reports from the Project List.
Check Summary Preview (Software Format; Auto-Populated)
| Check item | Trial value | Status |
|---|---|---|
| Wall flexural strength φMn ≥ LF·Mmax | 851.7 kN·m/m ≥ 518.2 | OK |
| Wall shear strength φVn ≥ LF·Vmax | 833.6 kN/m ≥ 273.1 | OK |
| Max wall deflection ≤ 0.50% of final excavation depth (control value) | 6.3 mm ≤ 40.0 | OK |
- US OSHA / State Plan — 29 CFR 1926.652(b)-(c); Subpart P Appendix B, Table B-1, Note 3: Sloping or benching for excavations greater than 20 ft deep must be designed by a registered professional engineer (Subpart P Appendix B, Table B-1, Note 3). A support or shield system not taken from Appendices C-D or from tabulated data must be approved by a registered professional engineer, and a copy of the design kept at the jobsite (1926.652(c)). (Depth > 20 ft; 26.25 ft)
Summary of the online calculation (software format) for checking by the designer and an independent checker. Final submittals require review and seal by the licensed Professional Engineer in responsible charge.
Desktop edition: calculation reports and cross-module quantity reconciliation
1. Calculation reports: with a license, the desktop edition writes Word (.docx) and Excel (.xlsx) calculation reports and DXF drawings without the trial watermark, listing the inputs, the equations used and the results; in trial mode the step-by-step detail is hidden. For this calculator alone, licensed users can also sign in on the calculator above and formally export a single-tool Word report (with a verification code) and DXF drawing. The Pro plan (all modules) is US$990 per year; see Pricing for monthly, perpetual and team plans.
2. Cross-module reconciliation: desktop project runs carry the design peak flow into downstream channel, culvert and bridge hydraulics; terrain cut/fill into the earthwork balance, cost and carbon tables; structural concrete, formwork and rebar take-off into the cost and carbon tables; slope and excavation safety-factor thresholds into construction monitoring trigger levels.
3. Agency plan reviewers and university faculty can request a complimentary review or teaching license (link below).
Standard example (calculation core defaults)
The worked example below was computed by the calculation core when this page was built; entering the same inputs above reproduces it. Verification cases, tolerances and actual differences for the calculation core are listed on the Benchmarks page.
The standard example uses the default inputs of the calculation core. Every number below was produced by the core when this page was built; nothing on this page is computed by hand.
Every number in this example was produced by the calculation core (WebAssembly) when this page was built. This calculator computes to the documents named in its basis line and works in SI units; use the unit button in the calculator to view US customary equivalents. Basis reported by the core: Taiwan Building Foundation Design Code (2023) commentary 8.7.3, Fig. C8.7-5 elasto-plastic subgrade reaction method; Taiwan Design Code for Concrete Structures (2023; ACI 318-19 framework) Chs. 21, 22
1. Input Parameters
| Design Parameter | Value | Unit |
|---|---|---|
| Diaphragm Wall Thickness t | 0.8 | m |
| Wall Toe Depth L (from ground surface) | 18 | m |
| Groundwater Depth on Retained Side | 3 | m |
| Surface Surcharge q | 10 | kPa |
| Layer 1 Bottom Depth | 9 | m |
| Layer 1 Unit Weight γt | 18 | kN/m³ |
| Layer 1 Saturated Unit Weight γsat | 19.5 | kN/m³ |
| Layer 1 Friction Angle φ′ | 32 | ° |
| Layer 1 Cohesion c′ | 2 | kPa |
| Layer 1 Horizontal Subgrade Reaction kh | 20000 | kN/m³ |
| Layer 2 Unit Weight γt | 19.5 | kN/m³ |
| Layer 2 Saturated Unit Weight γsat | 21 | kN/m³ |
| Layer 2 Friction Angle φ′ | 34 | ° |
| Layer 2 Cohesion c′ | 5 | kPa |
| Layer 2 Horizontal Subgrade Reaction kh | 26000 | kN/m³ |
| Stage 1 Excavation Depth | 2 | m |
| Stage 2 Excavation Depth | 5 | m |
| Strut 1 Installation Depth | 1 | m |
| Strut 1 Axial Stiffness | 50000 | kN/m/m |
| Strut 1 Preload | 50 | kN/m |
| Stage 3 Final Excavation Depth | 8 | m |
| Strut 2 Installation Depth | 4 | m |
| Strut 2 Axial Stiffness | 50000 | kN/m/m |
| Strut 2 Preload | 80 | kN/m |
| Concrete Strength fc′ | 280 | kgf/cm² |
| Rebar Yield Strength fy | 4200 | kgf/cm² |
| Cover | 9 | cm |
| Main Bar Size (both faces) | D25 (#8) | — |
| Main Bar Spacing | 15 | cm |
| Shear Tie Bar Size | D13 (#4) | — |
| Vertical Spacing of Shear Ties | 25 | cm |
| Horizontal Spacing of Shear Tie Legs | 30 | cm |
| Load Factor on Lateral Earth and Water Pressure LF | 1.6 | — |
| Flexural Stiffness Factor | 0.7 | — |
| Deflection Control Value | 0.5 | % |
2. Computed Results (calculation core output)
| Output | Result |
|---|---|
| Max flexural utilization Mu/φMn | 0.608 |
| Max shear utilization Vu/φVn | 0.328 |
| Envelope max deflection | 6.3 mm |
| Factored max moment Mu | 518.2 kN·m/m |
| Design flexural strength φMn | 851.7 kN·m/m |
| Factored max shear Vu | 273.1 kN/m |
| Design shear strength φVn | 833.6 kN/m |
| Rebar estimate (per m of wall) | 1241.0 kg/m |
| Concrete (per m of wall) | 14.40 m³/m |
Verification Checks (calculation core output)
| Verification Item | Computed Result | Governing Limit / Criterion | Status | Basis |
|---|---|---|---|---|
| Wall flexural strength φMn ≥ LF·Mmax | 851.7 kN·m/m | ≥ 518.2 | PASS | Taiwan Design Code for Concrete Structures (2023) |
| Wall shear strength φVn ≥ LF·Vmax | 833.6 kN/m | ≥ 273.1 | PASS | Taiwan Design Code for Concrete Structures (2023) |
| Max wall deflection ≤ 0.50% of final excavation depth (control value) | 6.3 mm | ≤ 40.0 | PASS | The deflection control value is an input (not a statutory limit; set it from the protection needs of adjacent structures) |
3. Calculation Steps (calculation core output, SI units)
[HyGeoWorks online preview - not for PE sealing or submittal] Wall thickness t = 0.80 m (effective depth d = 71.0 cm); flexural stiffness EI = 0.70·Ec·Ig = 735153 kN·m²/m Envelope max deflection δmax = 6.3 mm; factored max moment Mu = 518.2 kN·m/m (φMn = 851.7); max shear Vu = 273.1 kN/m (φVn = φVc 463.1 + φVs 370.5 = 833.6) Provided bars: main bars each face D25@15.0 cm (33.78 cm²/m); shear ties D13 at 25.0 cm vertically and 30.0 cm horizontally
Staged excavation elasto-plastic analysis summary (unfactored) (3 rows)
| Stage | Max deflection (mm) | +Mmax (kN·m/m) | −Mmax (kN·m/m) | Vmax (kN/m) | Passive mobilization (%) | Latest strut force |
|---|---|---|---|---|---|---|
| Stage 1 (2.0 m) | 1.3 | 21.9 | 0.0 | 13.0 | 31.9 | Cantilever |
| Stage 2 (5.0 m) | 2.3 | 37.5 | -141.5 | 64.7 | 41.6 | 73 kN/m |
| Stage 3 (8.0 m) | 6.3 | 79.6 | -323.9 | 170.7 | 56.5 | 202 kN/m |
Assumptions and Limits Stated by the Calculation Core
- Model: the elasto-plastic model of the Taiwan Building Foundation Design Code (2023) commentary 8.7.3, Fig. C8.7-5 - at zero wall displacement both sides carry at-rest earth pressure, which varies linearly with displacement and is limited by the active and passive pressures; surcharge and water pressure are superimposed on the earth pressure
- The horizontal subgrade reaction coefficient kh is an input: the code commentary notes that it is extremely hard to determine and must be judged from monitoring results of many actual sites, so no built-in values are provided. Results are sensitive to kh; a sensitivity analysis and back-analysis from monitoring data are advised
- Active and passive pressures use Rankine (no wall friction or adhesion); undrained layers use total stress (σ ∓ 2su); water pressure on both sides is hydrostatic with no seepage; earth pressure depends only on total displacement, with no unloading-reloading hysteresis
- At-rest pressure on the excavation side is based on the effective overburden stress after excavation (K0·σv′): unloading makes the at-rest pressures on the two sides unbalanced at depth and causes displacement; residual lateral stress after unloading is ignored, which is conservative for displacement at depth
- Not included: strut removal and floor slab construction stages, temperature effects, earthquake, stiffness reduction after wall cracking (reduce EI as appropriate), three-dimensional corner effects; embedment, basal heave, piping and uplift stability are checked separately per 8.8
- Wall reinforcement: the envelope moments of all stages are multiplied by the load factor and the required steel area (per metre width) is found by strength design; shear is compared with the concrete design shear strength; minimum reinforcement, development, lap splices and cage detailing are checked separately
- The flexural stiffness factor 0.70 is an input: for walls, Table 6.6.3.1.1(a) of the concrete code gives 0.70 Ig uncracked and 0.35 Ig cracked; Ec = 15000√fc′ (kgf/cm²)
- Shear strength is φ(Vc + Vs): Vc = 0.53√fc′·b·d; Vs from the entered ties (4.22 cm² per m of wall at 25.0 cm vertical spacing), with tie yield strength capped at 4200 kgf/cm²; minimum shear reinforcement and spacing limits are checked separately
- The rebar quantity is an estimate (not a bar schedule): main bars on both faces over the full depth plus 12% for laps, tie length taken as 90% of the wall thickness; horizontal bars, cage stiffeners and lifting bars are not included
Frequently Asked Questions
Common questions about this calculator and its basis are answered below. Final submittals require review and seal by a licensed Professional Engineer.
Which design basis does this calculator apply?
Taiwan Building Foundation Design Code (2023) commentary 8.7.3, Fig. C8.7-5 elasto-plastic subgrade reaction method; Taiwan Design Code for Concrete Structures (2023; ACI 318-19 framework) Chs. 21, 22. The analysis method and the reinforced concrete checks follow the Taiwan codes named in the basis line. Two soil layers, three excavation stages and two strut levels are modelled. The deflection control value (default 0.5% of the final excavation depth) and the flexural stiffness factor (default 0.70 Ec·Ig) are inputs, not statutory limits. Strengths are entered in kgf/cm².
What assumptions and limits does the calculation core state for this tool?
Model: the elasto-plastic model of the Taiwan Building Foundation Design Code (2023) commentary 8.7.3, Fig. C8.7-5 - at zero wall displacement both sides carry at-rest earth pressure, which varies linearly with displacement and is limited by the active and passive pressures; surcharge and water pressure are superimposed on the earth pressure. The horizontal subgrade reaction coefficient kh is an input: the code commentary notes that it is extremely hard to determine and must be judged from monitoring results of many actual sites, so no built-in values are provided. Results are sensitive to kh; a sensitivity analysis and back-analysis from monitoring data are advised. Active and passive pressures use Rankine (no wall friction or adhesion); undrained layers use total stress (σ ∓ 2su); water pressure on both sides is hydrostatic with no seepage; earth pressure depends only on total displacement, with no unloading-reloading hysteresis. At-rest pressure on the excavation side is based on the effective overburden stress after excavation (K0·σv′): unloading makes the at-rest pressures on the two sides unbalanced at depth and causes displacement; residual lateral stress after unloading is ignored, which is conservative for displacement at depth. Not included: strut removal and floor slab construction stages, temperature effects, earthquake, stiffness reduction after wall cracking (reduce EI as appropriate), three-dimensional corner effects; embedment, basal heave, piping and uplift stability are checked separately per 8.8. Wall reinforcement: the envelope moments of all stages are multiplied by the load factor and the required steel area (per metre width) is found by strength design; shear is compared with the concrete design shear strength; minimum reinforcement, development, lap splices and cage detailing are checked separately. The flexural stiffness factor 0.70 is an input: for walls, Table 6.6.3.1.1(a) of the concrete code gives 0.70 Ig uncracked and 0.35 Ig cracked; Ec = 15000√fc′ (kgf/cm²). Shear strength is φ(Vc + Vs): Vc = 0.53√fc′·b·d; Vs from the entered ties (4.22 cm² per m of wall at 25.0 cm vertical spacing), with tie yield strength capped at 4200 kgf/cm²; minimum shear reinforcement and spacing limits are checked separately. The rebar quantity is an estimate (not a bar schedule): main bars on both faces over the full depth plus 12% for laps, tie length taken as 90% of the wall thickness; horizontal bars, cage stiffeners and lifting bars are not included.
Where is the calculation performed, and can the result be sealed or submitted?
The calculation runs in your browser, in the same WebAssembly calculation core this page loads. The result is an online preview: its first line reads "[HyGeoWorks online preview - not for PE sealing or submittal]".
Can I recalculate without a network connection?
Yes. "Download the offline workbench" on this page saves one HTML file that contains the workbench and the same calculation core; opened from disk it recalculates without a network connection.
From the Online Preview to the HydroStudio Desktop Edition: Reports Without the Trial Watermark
The free online preview is not for PE sealing or submittal and has no Word report, DXF drawing or verification code. Licensed users can sign in on the calculator and formally export a single-tool Word report (with a verification code) and DXF drawing. Several calculators can be combined in the Project List and exported online as a multi-chapter project report, and projects with terrain or GIS files can run in the heavy cloud computation. For interactive 2D models and large simulations, the HydroStudio desktop edition (Windows 10/11, 64-bit) opens the exported .toml project and, with a license, writes report.docx, a report.xlsx with live formulas and DXF drawings without the trial watermark. Sealing and submittal remain the responsibility of the licensed engineer.
Compare all plans, including 90-day passes and perpetual licenses