Check Summary Preview (Software Format; Auto-Populated)
| Check item | Trial value | Status |
|---|---|---|
| Allowable Headwater Elevation | Design headwater elevation 51.655 m (Inlet Control) ≤ maximum allowable headwater elevation 52.000 m | OK |
| Headwater ratio HW/D | HW/D = 1.103 — | ◇ Not judged Not judged: No HW/D limit is set (this case HW/D = 1.103). HDS-5 §2.2.5 notes that the allowable HW/D varies by agency and commonly ranges from 1.0 to 1.5, while the MOTC (Taiwan) Highway Drainage Design Code 6.2.1 item 4 says it should be kept at 1.5 or above; because the two differ in direction, this tool does not judge HW/D. Set an HW/D upper limit to your agency's requirement. |
Summary of the online calculation (software format) for checking by the designer and an independent checker. Final sign-off remains the responsibility of the chartered or registered engineer.
Desktop edition: calculation reports and cross-module quantity reconciliation
1. Calculation reports: with a licence, the desktop edition writes Word (.docx) and Excel (.xlsx) calculation reports and DXF drawings without the trial watermark, listing the inputs, the equations used and the results; in trial mode the step-by-step detail is hidden. For this calculator alone, licensed users can also sign in on the calculator above and formally export a single-tool Word report (with a verification code) and DXF drawing. The Pro plan (all modules) is US$990 per year; see Pricing for monthly, perpetual and team plans.
2. Cross-module reconciliation: desktop project runs carry the design peak flow into downstream channel, culvert and bridge hydraulics; terrain cut/fill into the earthwork balance, cost and carbon tables; structural concrete, formwork and rebar take-off into the cost and carbon tables; slope and excavation safety-factor thresholds into construction monitoring trigger levels.
3. Independent checking engineers, authority reviewers and academics can request a complimentary review or teaching licence (link below).
1. Governing Equations & SI Nomenclature
The equations the calculation core applies are summarised below for independent checking.
The equations below summarise the method that the calculation core applies on this page. The design basis it reports is: FHWA HDS-5 Hydraulic Design of Highway Culverts (3rd Ed., 2012) & HY-8 v7.5 Energy Formulations. The worked example further down lists the core's own calculation steps for the standard example.
2. Worked Standard Example (Computed by the Calculation Core)
The worked example below was computed by the calculation core when this page was built; entering the same inputs above reproduces it.
Design Scenario — 2.0 × 1.5 m Box Culvert, Square-Edged Headwall (Q = 6.0 m³/s, L = 25 m): Find the governing headwater elevation, HW/D and outlet velocity of a 25 m long single-cell 2.0 m × 1.5 m box culvert (n = 0.013, invert 50.00 m to 49.75 m, tailwater depth 0.90 m) with a square-edged headwall and 90° and 15° wingwall flare (HDS-5 Chart 8, scale 2) carrying 6.0 m³/s, against an allowable headwater elevation of 52.00 m.
The inputs below were passed to the calculation core (WebAssembly) when this page was built; every step, result and check shown here is the core's own output. Basis reported by the core: FHWA HDS-5 Hydraulic Design of Highway Culverts (3rd Ed., 2012) & HY-8 v7.5 Energy Formulations
Inputs Passed to the Calculation Core
| Parameter | Value | Unit |
|---|---|---|
| Cross-Section Shape | Box Section | — |
| Clear Span B | 2 | m |
| Clear Rise D | 1.5 | m |
| Inlet Configuration (HDS-5 chart / scale) | Chart 8 scale 2: box, wingwall flare 90° and 15° (square-edge headwall) | — |
| Inlet Control Method | HY-8 polynomial | — |
| Design Discharge Q | 6 | m³/s |
| Manning n | 0.013 | — |
| Culvert Length L | 25 | m |
| Inlet Invert Elevation ELi | 50 | m |
| Outlet Invert Elevation ELo | 49.75 | m |
| Tailwater Depth TW | 0.9 | m |
| Allowable Headwater Elevation | 52 | m |
| Custom HW/D Upper Limit | (blank) | — |
Calculation Steps (calculation core output)
[HyGeoWorks online preview - not for PE sealing or submittal]
- Inlet control (HY-8 fifth-order polynomial): HWi = 1.655 m (HWi/D = 1.103, HY-8 fifth-order polynomial (Box Eq 1))
- Outlet control: V = Q/A = 2.000 m/s; H = (1 + Ke + Ku·n²·L/R^1.33)·V²/2g = (1 + 0.5 + 0.2560)×0.2039 = 0.358 m; dc = 0.972 m; ho = 1.236 m (ho = (dc + D)/2); HWo = ho + H − L·S = 1.344 m
- Governing control: Inlet Control; outlet velocity for inlet control: velocity at normal depth (HDS-5 p106 (3.24))
Computed Results (calculation core output)
| Output Parameter | Calculated Value | SI Unit |
|---|---|---|
| Inlet-Control Headwater HWi | 1.655 | m |
| Outlet-Control Headwater HWo | 1.344 | m |
| Controlling Headwater HW | 1.655 | m |
| Headwater Elevation EL_HW | 51.655 | m |
| Headwater Ratio HW/D | 1.103 | — |
| Outlet Velocity V_out | 4.27 | m/s |
Verification Checks (calculation core output)
| Verification Check | Computed Value | Criterion | Verdict | Basis |
|---|---|---|---|---|
| Allowable Headwater Elevation | Design headwater elevation 51.655 m (Inlet Control) | ≤ maximum allowable headwater elevation 52.000 m | OK | MOTC (Taiwan) Highway Drainage Design Code (2018) 6.2.1 items 1 and 3; HDS-5 §2.2.5 |
| Headwater ratio HW/D | HW/D = 1.103 | — | ◇ Not judged Not judged: No HW/D limit is set (this case HW/D = 1.103). HDS-5 §2.2.5 notes that the allowable HW/D varies by agency and commonly ranges from 1.0 to 1.5, while the MOTC (Taiwan) Highway Drainage Design Code 6.2.1 item 4 says it should be kept at 1.5 or above; because the two differ in direction, this tool does not judge HW/D. Set an HW/D upper limit to your agency's requirement. | — |
Barrel Elevation Profile (Sta. 0 = Inlet) (3 rows)
| Feature | Inlet | Outlet |
|---|---|---|
| Invert EL (m) | 50.000 | 49.750 |
| Crown EL (m) | 51.500 | 51.250 |
| HW / TW EL (m) | 51.655 | 50.650 |
3. Regional Design Options in This Edition: UK, EU, Singapore, Malaysia, Hong Kong & Australia
Symbols and units are SI unless stated otherwise.
- This calculator: the design basis is the one reported by the calculation core: FHWA HDS-5 Hydraulic Design of Highway Culverts (3rd Ed., 2012) & HY-8 v7.5 Energy Formulations. The options listed below belong to the calculators named in each item.
- United Kingdom, Ireland & European Union: The retaining wall and slope stability calculators default to EN 1997-1:2004 Design Approach 1 (Combination 1 & Combination 2); the UK National Annex and 2nd-Gen EN 1997-1:2024 / EN 1997-3:2025 (MFA, and RFA for retaining walls) are selectable there, as are DA2 for retaining walls and DA3 for slopes. The retaining wall calculator lets γG, γQ and γφ' be overridden for a National Annex and designs metric H-bars (H10–H32) when concrete and steel strengths are entered.
- Singapore & Malaysia: The retaining wall calculator offers SS EN 1997-1:2010 with the Singapore National Annex, and the detention calculator offers a DID Malaysia MSMA 2nd Edition (2012) Equation 2.2 IDF rainfall mode besides directly entered design intensities.
- Hong Kong SAR: HyGeoWorks does not claim Hong Kong Buildings Department pre-accepted program status; the retaining wall calculator's HK GEO Geoguide 1 option shows the calculation core's steps and checks so that the result can be checked independently. With that option the calculation core applies the Geoguide 1 Table 6 and Table 7 partial factors at ULS and the §9.2.4 middle-third eccentricity check at SLS.
- Australia & New Zealand: No ARR 2019 IFD data is built in; design rainfall intensities for any AEP can be entered directly in the detention calculator. The HydroStudio desktop edition supports GDA2020 / MGA2020 zones 46–59 as well as WGS 84 / UTM zones.
4. Frequently Asked Questions
Common questions about this calculator are answered below. Final sign-off remains the responsibility of the chartered or registered engineer.
Why is the governing headwater the larger of HWi and HWo?
HWi is the head needed to pass the flow through the entrance; HWo is the head needed to overcome tailwater, barrel friction and entrance and exit losses. The culvert operates under whichever control needs the higher upstream water level, so the calculation core adopts the larger value.
Is an HW/D limit applied?
No. The calculation core checks the headwater elevation against the allowable elevation you enter, and notes that HDS-5 §2.2.5 states the allowable HW/D ratio varies and commonly ranges from 1.0 to 1.5. Apply the HW/D limit of your authority, if any, to the HW/D value reported.
How can headwater be reduced when inlet control governs?
Under inlet control the barrel roughness and length have little effect. Enlarging the opening (or adding a cell) or improving the entrance, for example with bevelled edges or a different wingwall arrangement, lowers the headwater; select the corresponding HDS-5 chart and scale to compare.
Which inlet configurations are available?
The inlet configuration follows the HDS-5 charts and scales, for example concrete pipe with a square-edged or groove-end headwall, and box culverts with 30° to 75°, 90° and 15°, or 0° wingwall flares. Inlet control can be computed with the HY-8 polynomial or with the HDS-5 equations (A.1)–(A.3).